3 ptsA,B,C,D,T,AM,A1,A2,B1,C1,D1Official number: 2472
Are you allowed to drive onto the level crossing when the barriers are not fully lifted?
Description
Art. 28 para. 1 and para. 3 pt. 1 of the Act of 20 June 1997 - Road Traffic Act (Journal of Laws of 2012, item 1137, as amended).
Explanation
Correct answer: No
No, entering the railway crossing is only permitted after the barriers have been fully raised. As stated in Art. 28 para. 3 of the Road Traffic Act, it is forbidden to enter the crossing if the raising of the barriers has not been completed. Such a manoeuvre is extremely dangerous.
← Previous question
In the presented situation, are you obliged to stop and take an interest in this person?
Next question →
In the presented situation the engine will not start and you have no possibility of removing the vehicle from the track-way. Are you obliged to warn the driver of the rail vehicle of danger?